The Engineering Department is responsible for planning and managing the City's Capital Improvement Program (CIP), by preparing (or coordinating) engineering plans, specifications, cost estimates, and bid documents, and by inspecting and administrating construction contracts for CIP projects.


SLATE CREEK / MORGAN RANCH LIFT STATION IMPROVEMENT PROJECT

Description:
Rehabilitate the Morgan Ranch and Slate Creek Lift Stations

Contractor: Clyde G. Steagall, Inc
Status:        Construction is Complete

WASTEWATER TREATMENT PLANT DENITRIFICATION & UV DISINFECTION

Description: Installation of UV Disinfection Facility

Contractor: Syblon Reid
Status:        Construction Completed August 2009

2009 STREET REHABILITATION PROJECT

Description:
 Pavement reconstruction along South Auburn Street

Contractor: Simpson & Simpson
Status:        Construction Completed September 2009

2009 SLURRY PROJECT

Description:
 Slurry and striping along East Empire Street and in the Carriage House Subdivision

Contractor: California Pavement Maintenance (CPM)
Status:        Construction Completed October 2009

ALTA WATER TANKS PROJECT

Description:
Install Two One-Million-Gallon Steel Water Tanks and Retrofit the Gravity Filter Backwash Station

Work in Progress

Contractor: Mountain Cascade, Inc.
Status: Construction is on schedule and is anticipated to be completed in December 2009

2007/2008 SIDEWALK PROJECT
Description: Install/repair sidewalk at various City locations

Contractor: DMCE
Status:        Construction should be completed by December 31, 2009

EAST MAIN STREET WIDENING PROJECT

Description:
 Widening of East Main Street between Richardson & Murphy Streets

Contractor: C & D contractors
Status:        Construction is estimated to be complete by January 2010

2008 WATER PROJECT

Description:
Replacement of water line in Berryman Street

Contractor: TBD
Status:        Scheduled to Bid Winter 2010 with Construction Spring 2010

ARRA STREET REHABILITATION PROJECT

Description:
Pavement reconstruction and overlay along South Auburn Street

Contractor: TBD
Status:        Under Design.  Scheduled to Bid early 2010 with Construction Spring 2010

MEMORIAL AND MAUTINO PARK SHADE STRUCTURES

Description:
Install shade structures

Contractor: TBD
Status:        Under Design.  Scheduled to Bid early 2010 with Construction Spring 2010

MEMORIAL PARK ACCESSIBILITY IMPROVEMENTS

Description:
Sidewalk and parking improvements

Contractor: TBD
Status:        Under Design.  Scheduled to Bid early 2010 with Construction Spring 2010

MEMORIAL PARK CLUB HOUSE

Description:
Rehabilitate existing Club House

Contractor: TBD
Status:        Under Design.  Scheduled to Bid early 2010 with Construction Spring 2010

2008 FLOOD DAMAGE

Description:
Matson Creek and East Main Street storm drainage repairs

Contractor: TBD
Status:        Under Design.  Scheduled to Bid early 2010 with Construction Summer 2010

SR2S - WEST MAIN STREET

Description:
Sidewalk improvements and pavement rehabilitation on West Main Street between Alta Street and the west City Limits

Contractor:
TBD
Status:        Design Spring 2010.  Scheduled to Bid early 2010 with Construction Summer 2010

2008 SEWER PROJECT

Description:
Replacement of sewer line from Brighton Street (market) to St. Patrick's Drive.

Contractor: TBD
Status:        Scheduled to Bid 2010 with Construction 2010

 
 
 
 
 